There are five processes A to E to run. Their burst times are 3,4,5,2 and 3 seconds respectively. Their arrival times are 0,1,5,5 and 7 seconds respectively. What is the average waiting time using First-come-First-served, shortest job first and round robin (with 2 second quantum scheduling?)