Question 6. A project consists of three tasks as shown in the table below. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 3. Task B is scheduled to begin at the start of Week 2 and finish at the end of Week 4. Task C is scheduled to begin at the start of Week 3 and end at the end of Week 4. The budgeted cost for Task A is $60,000, for Task B is $46,000, and for Task C is $28,000. At the end of the third week, Task A is 90% complete, Task B is 80% complete, and Task C is 70% complete. Please answer the following questions. [10 points) a) Develop a cost-loaded schedule (the table below) Schedule and Costs Cost-Loaded Schedule Week Week Cost (S) Task Cost (%) Start Finish Task A 60,000 1 3 Task B 46,000 2 4 4 Task C 28,000 3 4 1 2 3 b) What is the SPI for the project at the end of the third week? c) If the ACWP at the end of the third week for the project is $96,300, determine the CPI for the project d) Determine the total estimated cost at completion and the cost to complete the cost after the end of the third week), assuming the CPI remains the same through the project. Question 6. A project consists of three tasks as shown in the table below. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 3. Task B is scheduled to begin at the start of Week 2 and finish at the end of Week 4. Task C is scheduled to begin at the start of Week 3 and end at the end of Week 4. The budgeted cost for Task A is $60,000, for Task B is $46,000, and for Task C is $28,000. At the end of the third week, Task A is 90% complete, Task B is 80% complete, and Task C is 70% complete. Please answer the following questions. [10 points) a) Develop a cost-loaded schedule (the table below) Schedule and Costs Cost-Loaded Schedule Week Week Cost (S) Task Cost (%) Start Finish Task A 60,000 1 3 Task B 46,000 2 4 4 Task C 28,000 3 4 1 2 3 b) What is the SPI for the project at the end of the third week? c) If the ACWP at the end of the third week for the project is $96,300, determine the CPI for the project d) Determine the total estimated cost at completion and the cost to complete the cost after the end of the third week), assuming the CPI remains the same through the project