Question 6 ALA BERHAD manufactures two products Cutie Pie and Sweetie Pie. Product Cutie Pie and Sweetie Pie used two types of material CC and
Question 6
ALA BERHAD manufactures two products Cutie Pie and Sweetie Pie. Product Cutie Pie and Sweetie Pie used two types of material CC and DD. The following projected data for the month of March 2019 are as follows:
| Product | |
Cutie Pie | Sweetie Pie | |
Production cost per unit (RM) | 700 | 600 |
Sales (unit) | 2,000 | 3,000 |
Standard selling price per unit (RM) | 1,200 | 1,000 |
The stock of the products and materials are:
| Product | Material | ||
Stock at standard cost | Cutie Pie (RM) | Sweetie Pie (RM) | CC (RM) | DD (RM) |
28 February | 280,000 | 480,000 | 120,000 | 250,000 |
31 March | 350,000 | 660,000 | 144,000 | 272,000 |
Additional information for each unit of product Cutie Pie and Sweetie Pie is as follows:
|
| Product | |
Price / Rate | Cutie Pie | Sweetie Pie | |
Direct material: CC DD |
RM6 per meter RM8 per unit |
24 meters 10 units |
30 meters 8 units |
Direct wages: Unskilled Skilled |
RM5 per hour RM9 per hour |
10 hours 6 hours |
7 hours 5 hours |
Required:
Using the information given above, you are required to prepare for the month of March 2019:
- Sales budget.
(3 marks)
- Production budget (unit)
(4 marks)
- Direct material usage and purchase budget.
(8 marks)
- Direct labour budget.
(5 marks)
Qswana ALBER D minutectures were cu Readcore Pe Froduct Oute Fle and Sweetie Ple used two ypes of real Can Do The town stats for the month of March 2019 ans as tolong Procu! CAPIR SPA Production cost ser un Sa sunt 3.0.0 2005 1,2000 Sebarang penuh RM 1000 The usku PREEXNmber Product Sock winter Cut PH MMO Smartie Pier COM 23 FLAT 222.000 2:00 ,000 2720 Add information for a chat produd Cute P i a a low Product Prics Ral Cutie Pie Direct material: per meter 24 stars 30 meters Meer un 10 units aunts Direct Wagas: U ohled 10 hours 7 hours RM per hour FM per hour Sklod Elours S hours Reged: using their stinger above. you are required to prepare for the month of March 2012 1 Babel thi Protection budget int! 16) Direct material usage and prchase budget Idi Direct labour budget. (20 Marka) (4 mi mark markStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started