QUESTION 6 If the IRR for a project is 18%, then the project's NPV would be A. positive at a discount rate of 25% B.
QUESTION 6 If the IRR for a project is 18%, then the project's NPV would be A. positive at a discount rate of 25% B. negative at a discount rate of 18% C. positive at a discount rate of 8% D. positive at a discount rate of 20% RICTION Save and submit to save and submit. Click Save All Answers to save all answers