Question

1 Approved Answer

Question 6: Project ABC is planned for 15 months with a budget (BAC) of $150,000. If the scheduled percent of work completed after three months

Question 6: Project ABC is planned for 15 months with a budget (BAC) of $150,000. If the scheduled percent of work completed after three months is 20% and the actual work completion is 15%, what is the schedule variance? What is the SPI? How is the project doing compared to the planned schedule? Your answers here (show your work)

Question 7: Project ABC is planned for 15 months with a budget (BAC) of $150,000. The scheduled percentage of work completed after three months is 20% and the actual work completion is 35%. The amount spent to date is $40,000. What is the cost variance? What is the CPI? How is the project doing when compared with the planned budget costs?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology for Management Digital Strategies for Insight Action and Sustainable Performa

Authors: Efraim Turban, Carol Pollard, Gregory Wood

10th edition

1118994299, 1118994290, 1118897781, 9781118897782, 978-1118994290

More Books

Students also viewed these General Management questions

Question

Write the deferred acceptance algorithm in pseudocode.

Answered: 1 week ago