Question 8 ( 2.75 points) Table 1 Using the data in Table 1 above, what is the latest possible time that C may be started

image text in transcribed

Question 8 ( 2.75 points) Table 1 Using the data in Table 1 above, what is the latest possible time that C may be started without delaying completion of the project (i.e., LS for activity C)? 8 5 6 10 4