Question
QUESTION 8 XYZ Company installs cable service for customers in Ashland, Ohio. In an attempt to better manage the material and labor cost on new
QUESTION 8
-
XYZ Company installs cable service for customers in Ashland, Ohio. In an attempt to better manage the material and labor cost on new cable installations, the company set the following standards for each cable installation:
Information for Material and Labor Standard Variations Standard Per Unit Output: Per Each Install Expected Price Direct Material 1 Install Kit $ 58.00 Direct Labor 1.5 Hrs $ 18.00 At the end of January, XYZ company had the following results:
Actual Results January: Number of Installs 350.00 Purchased & Used Actual Price Per Unit Direct Material 355.00 Install Kits $ 59.00 Actual Hours Used Actual Rate Per Hour Direct Labor Hours 522.00 Hrs $ 19.00 Based on this information, the Material Price Variance is ________________.
A. (355) Unfavorable
B. (355) Favorable
C. 200 Unfavorable
D. 200 Favorable
Q9:
Based on the information in Question 8, the Material Quantity Variance is ________________.
A. | (290) Unfavorable | |
B. | 270 Favorable | |
C. | 100 Favorable | |
D. | (300) Unfavorable |
Q10:
Based on the information in Question 8, the Labor Rate Variance is ________________.
A. | 500 Favorable | |
B. | (322) Unfavorable | |
C. | (122) Unfavorable | |
D. | (522) Unfavorable |
Q11:
-
Based on the information in Question 8, the Labor Quantity Variance is ________________.
A. 367 Favorable
B. 54 Favorable
C. 540 Favorable
D. 400 Favorable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started