Question #81 of 180 Question ID: 1630099 One of your project's tasks has an early start of week 9, an early finish of week
Question #81 of 180 Question ID: 1630099 One of your project's tasks has an early start of week 9, an early finish of week 15, a late start of week 12, and a late finish of week 18. What is the task's float? OA) 3 O B) 12 C) 6 OD) 9 Previous Question 81 4 of 180 Check for Review Next