Question
Question 81 pts The authors define this term as the time an activity can be delayed without affecting the start time of any successor activity.
Question 81 pts
The authors define this term as the time an activity can be delayed without affecting the start time of any successor activity.
Group of answer choices
Project Slack
Total Slack
Free Slack
Overhead Slack
Question 91 pts
"Activity 5 cannot begin until Activity 4 has been underway for at least 2 days" is which type of restriction?
Group of answer choices
Finish to Finish
Start to Finish
Finish to Start
Start to Start
Question 101 pts
What is the crash slope for an activity that normally costs $1,200 and takes 12 days but may be crashed to 7 days with a crash cost of $2,750?
Group of answer choices
310
None of the above are correct
1,550
-310
-1,550
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started