Question 9 1 pts Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below Activity Normal
Question 9 1 pts Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below Activity Normal Time Normal Cost Crash Duration Crash Cost 8 days $6,000 6 days $8,000 3 days $1,800 2 days $2,400 12 days $5,000 9 days $7,700 What is the crash cost of the activity that should be crashed first to cut one day from the project's duration? (answer format is XXX without the "$" sign)