Question 9 {2 points} Saved What is the duration of the project shown below (numbers are duration in days, and dependencies are all FinishtoStart AND
Question 9 {2 points} Saved What is the duration of the project shown below (numbers are duration in days, and dependencies are all FinishtoStart AND THERE IS A LAG OF 3 clays between D and F) (3. 23 days (3. 25 days .3. 27 days (3. 24 days