Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Question: A project precedence table with normal and crash times and cost is given in tables: Activity Predecessor Normal Time Crash Times Normal Crash (Weeks)
Question: A project precedence table with normal and crash times and cost is given in tables: Activity Predecessor Normal Time Crash Times Normal Crash (Weeks) (Weeks) Cost Cost (RS.) (RS) A - 4 2 8000 9000 B A 5 2 16000 20000 C A 4 1 12000 13000 D B,C 6 4 34000 35000 E A 6 4 42000 44000 E 5 3 16000 16500 G D,F 7 4 66000 72000 H G,D 4 2 2000 5000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started