Question

...
1 Approved Answer

Question As a contractor's quantity surveyor for a bungalow project, calculate the payment duetothecontractorbypreparingInterimCertificateno.4,giventhefollowinginformation: Accumulatedpayment paidtocontractor------------ $4,800,000 Variationwork (completed)------------ $7,800(Nettaddition) Limitofretention----------- 5%ofthe contractsum Retentiononworkdone----------- 10%

Question

As a contractor's quantity surveyor for a bungalow project, calculate the payment duetothecontractorbypreparingInterimCertificateno.4,giventhefollowinginformation:

  • Accumulatedpayment paidtocontractor------------ $4,800,000
  • Variationwork (completed)------------ $7,800(Nettaddition)
  • Limitofretention----------- 5%ofthe contractsum
  • Retentiononworkdone----------- 10%
  • Retentiononmaterialdeliveredtosite----------- 20%
  • Rentalofexcavatorforexcavationworks----------- $20,000
  • T20steelreinforcement barsdeliveredtosite------------ $55,000
  • Cementbagsdeliveredto site------------- $2,000
  • Cakesforsitemeetings-------------- $2,000
  • Paintorderedbutnotyet delivered------------- $15,000
  • Contractsum--------------- $50,000,000
  • Contractworkcompleted to-date:-------$6,100,000

Kindly show yourdetailedworkingsandpresent youranswerintheprescribed format

For me to understand and analyze. Thank you

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Real Analysis

Authors: Robert G. Bartle, Donald R. Sherbert

4th edition

978-0471433316

Students also viewed these General Management questions