Question: Question content area top Part 1 How does a job - costing system differ from a process - costing system? Question content area bottom Part
Question content area top
Part
How does a jobcosting system differ from a processcosting system?
Question content area bottom
Part
A
A processcosting system allocates indirect costs to products; a jobcosting system does not allocate indirect costs to products.
B
A jobcosting system allocates indirect costs to products; a processcosting system does not allocate indirect costs to products.
C
A jobcosting system assigns costs to distinct units; a processcosting system assigns costs to masses of similar units.
D
A jobcosting system assigns costs to masses of similar units; a processcosting system assigns costs to distinct units.