Question content area top Part 1 Lanny discovers that the bottleneck is the riveting machine so he schedules all production around when that machine is
Question content area top
Part
Lanny discovers that the bottleneck is the riveting machine so he schedules all production around when that machine is available. This is an example of elevating the constraint in the fivestep constraint management process.
Question content area bottom
Part
True