Question Content AreaWe identify the critical path of a project as a . the longest path through the project. b . the shortest path through
Question Content AreaWe identify the critical path of a project as
a the longest path through the project.
b the shortest path through the project.
c any path that goes from the starting node to the completion node.
d the combined time of all paths of the project.