QUESTION FIVE Sasumwa Construction limited has been awarded a contract to build a house. This is a contract No 45 for the company and the
QUESTION FIVE
Sasumwa Construction limited has been awarded a contract to build a house. This is a contract
No 45 for the company and the contract price is Shs.2.65 million. At the end of the company's
financial year, the contract was 85% complete and hence regarded as being near completion. You
are also provided with the following information about the contract:
Particulars Shs.
Materials purchased and delivered 580,000
Materials issued from store 60,000
Materials returned to stores 9,000
Site expenses 300,000
Site wages 200,000
Plant sent to site 100,000
Architect's fees 30,000
Plant returned from site 10,000
Subcontractor's fees 105,000
Head Office overheads absorbed 60,000
Valuation at the year ending disclosed the following: Shs
Materials: 19,500
Plant on site 50,000
Work done but not yet certified 60,000
Additional information
a) The portion of the work which was completed during the year and certified by the architect
was assessed as representing 75% of the whole contract price. The contractee made
payments to this extent less 10% retention money.
b) The management of the company decided for the purpose of preparing the company's
annual accounts to make a provision of a third of the notional profit against the possibility
of defects and other contingencies arising later in respect of the work already certified
for payment.
Required:
- Prepare the contract account
- Compute the amount of profit or loss to be taken to the main profit and loss account of
the company.
- Compute the value of work in progress.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started