QUESTION FOUR A project has the following characteristics: table [ [ Activity , Optimistic time,Pessimistic time,Mast likely time ] , [ 1 - 2

QUESTION FOUR
A project has the following characteristics:
\table[[Activity,Optimistic time,Pessimistic time,Mast likely time],[1-2,1,5,1.5],[2-3,1,3,2],[2-4,1,5,3],[3-5,3,5,4],[4-5,2,4,3],[4-6,3,7,5],[5-7,4,6,5],[6-7,6,8,7],[7-8,2,6,5],[7-9,5,3,5],[8-10,1,7,5],[9-10,3,,5]]
(a) Construct the network
(b) Find the critical path and variance for each event
(c) Find the project duration at 95% probability.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management

Authors: John Pearce , Richard Robinson

13th Edition

0078029295, 978-0078029295

More Books

Students also viewed these General Management questions

Question

What is continuous improvement and why is it important?

Answered: 1 week ago