QUESTION: Hanna Ltd. has the following information available for March: Total Total Budget Actual Units 2,500 2,800 Direct materials $8,125 $8,540 Direct labour $32,000 $36,680
QUESTION:
Hanna Ltd. has the following information available for March:
Total | Total | |
Budget | Actual | |
Units | 2,500 | 2,800 |
Direct materials | $8,125 | $8,540 |
Direct labour | $32,000 | $36,680 |
Variable overhead | $55,000 | $60,200 |
Fixed overhead | $77,500 | $92,400 |
Prepare a flexible budget at the actual output level and use the information to answer the following questions.
What is the total direct materials cost on the flexible budget?
What is the total direct labour costs on the flexible budget?
What is the total variable overhead costs on the flexible budget?
What is the total fixed overhead costs on the flexible budget?
What is the total production costs on the flexible budget?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started