The Armer Company is accumulating data to be used in preparing its annual profit plan for the coming year. The cost behavior pattern of the maintenance costs must be determined. The accounting staff has suggested that linear regression be employed to derive an equation in the form of y = a + bx for maintenance costs. Data regarding the maintenance hours and costs for last year and the results of the regression analysis are as follows:

Hours of Activity Maintenance Costs
January 490 $ 4,200
February 340 3,200
March 390 3,700
April 280 2,760
May 480 4,390
June 290 2,850
July 300 3,000
August 500 4,640
September 470 4,170
October 480 4,080
November 330 3,500
December 330 3,000
Sum 4,680 43,490
Average 390 3,624

A coefficient 776.61
B coefficient 7.3014
Standard error of the a cofficient 226.207
Standard error of the a cofficient 0.56703
Standard error of the estimate 164.926
R2 0.94312
T-value a 3.433
T-value b 12.877

Using the high-low method to estimate cost behavior, 500 maintenance hours in a month would mean the maintenance costs would be budgeted

i need help with this Question please

Question number 2:

The Armer Company is accumulating data to be used in preparing its annual profit plan for the coming year. The cost behavior pattern of the maintenance costs must be determined. The accounting staff has suggested that linear regression be employed to derive an equation in the form of y = a + bx for maintenance costs. Data regarding the maintenance hours and costs for last year and the results of the regression analysis are as follows:

Hours of Activity Maintenance Costs
January 460 $ 4,300
February 310 2,700
March 450 3,700
April 300 3,070
May 510 4,500
June 330 3,120
July 330 3,230
August 470 4,070
September 500 4,440
October 430 3,880
November 390 3,700
December 360 3,280
Sum 4,840 43,990
Average 403 3,666
A coefficient 653.76
B coefficient 7.4680
Standard error of the a cofficient 278.906
Standard error of the a cofficient 0.68053
Standard error of the estimate 171.443
R2 0.92333
T-value a 2.344
T-value b 10.974

What is the variable cost per hour using the high-low method to estimate the cost equation?

Question number 3:The Chambers Manufacturing Company recorded overhead costs of $16,091 at an activity level of 4,950 machine hours and $9,812 at 2,250 machine hours. The records also indicated that overhead of $10,050 was incurred at 2,975 machine hours. What is the variable cost per machine hour using the high-low method to estimate the cost?.

Question number 4:

The cost accountants at the Doering Company regressed total overhead costs and direct labor hours for the past 30-months and reported the following results:

Slope = $ 36.68
Intercept = $530.03
Correlation coefficient = 0.830

What is the estimated overhead cost if 203 direct labor hours are expected to be used in the upcoming period?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Information Systems

Authors: Robert Hurt

2nd Edition

78111056, 978-0078111051

More Books

Students also viewed these Accounting questions