Question One Kanduyi incorporation is bidding on a contract to repair and refurbish a dilapidated structure in Kibabii University. It has identified the following activities
Question One
Kanduyi incorporation is bidding on a contract to repair and refurbish a dilapidated structure in
Kibabii University. It has identified the following activities along with their predecessor
restrictions and expected times required to undertake each activity.
In addition to the above cost figures there are t indirect costs per day during the project.
a Using normal duration determine the total overall cost for the project and its duration.
mks
b Find the project duration that will minimize the total cost of the project. mks
c Determine the total cost of completing the project in the shortest possible time. mks
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started