Question One Kanduyi incorporation is bidding on a contract to repair and refurbish a dilapidated structure in Kibabii University. It has identified the following activities

Question One
Kanduyi incorporation is bidding on a contract to repair and refurbish a dilapidated structure in
Kibabii University. It has identified the following activities along with their predecessor
restrictions and expected times required to undertake each activity.
In addition to the above cost figures there are t60 indirect costs per day during the project.
a) Using normal duration determine the total overall cost for the project and its duration.
(10mks)
b) Find the project duration that will minimize the total cost of the project. (13mks)
c) Determine the total cost of completing the project in the shortest possible time. (2mks)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of Finance With Excel

Authors: Simon Benninga, Tal Mofkadi

3rd Edition

0190296380, 9780190296384

More Books

Students also viewed these Finance questions

Question

What online recruitment methods are available?

Answered: 1 week ago