Question Orville Company's standard and actual costs per unit are provided below for the most recent period. During this time period 400 units were
Question Orville Company's standard and actual costs per unit are provided below for the most recent period. During this time period 400 units were actually produced. Product Standard Product Actual Cost Cost Materials Standard Metres Unit Price Per Metre 3 $1.50 $4.50 Materials price variance = AQ (AP - SP) Materials quantity variance = SP (AQ-SQ) $124.00 U $60.00 U Actual 3.1 $1.60 $4.96 Direct labour Hours Hourly Rate Standard 2.4 $6.00 $14.40 Direct labour rate variance = AH (AR-SR) Direct labour efficiency variance = SR (AH-SH) $500.00 U $240.00 U Actual 2.5 $6.50 $16.25 Variable overhead Hours Hourly Rate Standard 1.5 $3.40 $5.10 Variable overhead rate variance = AH(AR-SR) Variable overhead efficiency variance = SR(AH-SH) -$168.00 F -$136.00 F Actual 1.4 $3.10 Total unit cost $24.00 $4.34 $25.55 Total Variance $620.00 U 400 AP*AQ-SP*SQ $620.00 U For simplicity, assume there was no inventory of materials at the beginning or end of the period. Required Given the information above, compute the following variances. Also indicate if the variances are favorable or unfavorable. 1. Materials price variance 2. Materials quantity variance 3. Direct labour rate variance 4. Direct labour efficiency variance 5. Variable overhead rate variance 6. Variable overhead efficiency variance =AP*AQ-AQ*SP+AQ*SP-SP*SQ =AQ(AP-SP)+SP(AQ-SQ) First keep AQ no change Then keep SP no change
Step by Step Solution
★★★★★
3.47 Rating (147 Votes )
There are 3 Steps involved in it
Step: 1
Variance Calculations for Orville Company 1 Materials Price Variance Favorable Following the formula AQAP SP SPAQ SQ AQ Actual Quantity 400 units AP Actual Price 160 per meter SP Standard Price 150 pe...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started