Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Question that pertains to the scenario below: If a composite labor rate, developed on the basis of the overall mix of work on the entire

Question that pertains to the scenario below: If a composite labor rate, developed on the basis of the overall mix of work on the entire contract, was used in the original estimate, should the same composite rate be used in pricing the work associated with the change?

In January 20X1, the ABC Company received a contract from the Air Force for 175 electronic devices. The contract was a firm fixed price contract at a unit price of $115,000, and a total price of $20,125,000. The price included a 12% profit. The delivery schedule called for 25 a month commencing in May 20X1, with delivery to be completed by December 20X1.

In July, a change was made by the Air Force in several of the components. At the time of the change the contractor had completed 75 but had not shipped any of the items. Another 50 units were partially completed. The components affected by the change were completed on 40 of the 50 items. Ten of the work-in-process items were not affected by the change. The contractor submitted the following cost proposal.

I. COMPLETED UNITS AFFECTED BY THE CHANGE

Labor

Removing changed work

New work

**Overhead @ 180%

Material

Manufacturing Cost

***G&A @ 15%

Profit @ 12%

Total cost of change per unit

90 hours

140 hours

230 hours @ $30.00*

$ 6,900.00

12,420.00

3,250.00

$ 22,570.00

3,385.50

$ 25,955.50

3,114.60

$ 29,070.10

Number of units affected by the change (75 + 40)

115

$3,343,061.50

*Labor estimated in the original contract @ $27.50 per hr.

**Overhead estimated in the original contract @ 110%

***G&A estimated in the original contract @ 6%

II. UNITS ON WHICH CHANGED WORK HAD NOT BEEN PERFORMED

Labor

New work

Less estimated cost of old work

Overhead @ 180%

Material

Less old material

Manufacturing Cost

G&A @ 15%

Total Cost

Profit @ 12%

Unit Cost of Change

140 hours

*40 hours

100 hours @ $30.00

$3,250.00

2,650.00

$ 3,000.00

5,400.00

600.00

$ 9,000.00

1,350.00

$ 10,350.00

1,242.00

$ 11,592.00

60 units on which none of the work affected by the

change had been performed

60

$695,520.00

Total cost of change ($3,343,061.50 + $695,520.00) $4,038,581.50

*This portion of the work had originally been estimated to take 70 hours

Mr. Roger Stinson, who was assigned the responsibility of negotiating the change, requested that an analysis be made of the contractor's proposal. Mr. Richard Foster was assigned to the case by the Cost Analysis Section. His report to Mr. Stinson disclosed the following points of difference.

1. REMOVING CHANGED WORK

Contractor's Proposal

90 hrs @ $30.00

Air Force

60 hrs @ $27.50

Mr. Stinson was of the opinion that the company had overestimated the amount of time required to remove the work affected by the change which had already been performed. His opinion was strengthened by the fact that the contractor estimated the time required to install the work at only 40 hours elsewhere in his proposal. The contractor informed him that there was no relation between the time required to install new work and the cost of removing the old work; that in this case a considerable amount of the changed work involved terminal block locations and wiring which was inaccessible without removing other work already installed.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Economics A Problem Solving Approach

Authors: Luke M. Froeb, Brian T. McCann, Mikhael Shor, Michael R. War

3rd edition

978-1133951483

Students also viewed these Law questions