Question Three Nyaweco Engineering Ltd has revealed that their maintenance cost incurred, and the actual machine hours worked during January, February, March, and April 2023
Question Three
Nyaweco Engineering Ltd has revealed that their maintenance cost incurred, and the actual machine hours worked during January, February, March, and April 2023 were as follows:
Month | Machine hours in production departments | Maintenance departments Cost in Kshs |
January | 800 | 350 |
February | 1200 | 350 |
March | 400 | 150 |
April | 1600 | 550 |
Required:
a) Find the cost estimation function using:
(i) High-low method
(ii) Regression analysis
b) Using the regression function above, estimate:
(i)The maintenance costs that would have been incurred if the machine hours were expected to be 900 in the month of May 2023.
(ii)The maximum machine hours that would have been worked If the maintenance cost incurred had been limited to Kes 400,000 for the month of May 2023
c) Assuming that in May 2023 machine hours were 900, show a 95% confidence interval for this point estimate
(Assume tc = 2.7764 and se = 63.25)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started