Question: You are the project manager of ABC project.Your BAC is $800,000. You have spent $270,000 of your budget. Youare now 30% done with the
Question: You are the project manager of ABC project.Your BAC is $800,000. You have spent $270,000 of your budget. Youare now 30% done with the project, and your plan called for you tobe 40% complete by this time. What is your SPI?
A. 1.00
B. 0.89
C. 0.75
D. Not enough information
Question: A project cost baseline is also calleda:
A. Planned Value
B. Actual Cost
C. Project Value
D. Both A and B are correct
E. A, B and C are all correct
Question: You have just started a project for amanufacturer. Project team members report they are 20% completewith the project. You have spent $25,000 of the project's $250,000budget. What is the earned value for this project?
A. 10 percent
B. $75,000
C. $50,000
D. Not enough information to know
Question: You have just started a project for amanufacturer. Project team members report they are 40% completewith the project. You have spent $25,000 of the project's $250,000budget. What is the earned value for this project?
A. $100,000
B. $75,000
C. $25,000
D. Not enough information
Step by Step Solution
3.42 Rating (146 Votes )
There are 3 Steps involved in it
Step: 1
1 B 2 E 3 D 4 C Explanation 1 The SPI is calculated by ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started