You have been asked to complete project in the shortest time possible. The project tasks' duration (in days), and predecessors are shown below.
Tasks | Duration | Predecessors |
A | 2 | None |
B | 2 | None |
C | 1 | None |
D | 4 | A |
E | 5 | B |
F | 1 | C, D |
G | 6 | A, E |
H | 4 | F |
I | 7 | G, H |
Answer the following questions:
1.which activities have highest and lowest slacK?
2. What are the different paths (sequence of tasks) to finish the above project and how many days does each path task?
3. What is the critical path, i.e., the shortest time in which the above whole project can be completed?
4.As a Project manager, what can you do to speedup project
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started