Question

1 Approved Answer

Question: You Have Been Asked To Complete A Project In The Shortest Time Possible. The Project Tasks' Duration (In Days), And Predecessors Are Shown Below.

Question: You Have Been Asked To Complete A Project In The Shortest Time Possible. The Project Tasks' Duration (In Days), And Predecessors Are Shown Below. Tasks Duration

You have been asked to complete project in the shortest time possible. The project tasks' duration (in days), and predecessors are shown below.

Tasks

Duration

Predecessors

A 2

None

B 2

None

C 1

None

D 4 A
E 5 B
F 1

C, D

G 6

A, E

H 4 F
I 7

G, H

Answer the following questions:

1.which activities have highest and lowest slacK?

2. What are the different paths (sequence of tasks) to finish the above project and how many days does each path task?

3. What is the critical path, i.e., the shortest time in which the above whole project can be completed?

4.As a Project manager, what can you do to speedup project

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Management Strategies

Authors: Ronald A Nykiel, Ronald A CHE CHA Nykiel PhD

1st Edition

0130618764, 9780130618764

More Books

Students also viewed these General Management questions

Question

Is there any other possible conclusion?

Answered: 1 week ago

Question

Go, do not wait until I come

Answered: 1 week ago

Question

Make eye contact when talking and listening

Answered: 1 week ago

Question

Do not go, wait until I come

Answered: 1 week ago