Question
Question3 A contractor wasawarded a tender. The Public Sector Standard Conditions of Contract(PSSCOC)forconstructionworks(8 th Edition,2020)wasusedforthecontract.Thefollowingsituations occurred during the construction period. Discuss whether the contractor would
Question3
A contractor wasawarded a tender. The Public Sector Standard Conditions of Contract(PSSCOC)forconstructionworks(8thEdition,2020)wasusedforthecontract.Thefollowingsituations occurred during the construction period. Discuss whether the contractor would beentitled to an extension oftime.
a) TheSuperintendingOfficer(SO)suspectedthatthequality ofconcretefortheconstructionoftenreinforcedconcrete(R.C.)columns didnotcomply withthecontract requirements.
(10marks)
b) An army helicopter crashed into the site and damaged a large part of the work.Theconstructionactivitieshadtobesuspendedfor20dayssothatasiteinvestigationcouldbeconducted.
(10marks.
c) A concrete supplier refused to supply ready-mix concrete to the site because theconcrete price between the contractor and the supplier was not finalized.This causedseveralstoppages tothe workanddelayedtheoverallcompletiondateforsixdays.
(10marks
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started