Question#5 Read the following set of activities carefully. The precedence of all activities is finish to start. Using either ADM or PDM, perform the following
Question#5
Read the following set of activities carefully. The precedence of all activities is finish to start. Using either ADM or PDM, perform the following tasks.
- Draw activity model
- Using forward pass, calculate earliest start and earliest finish for each activity
- Using backward pass, calculate latest start and latest finish of each activity. Determine float
- Represent Critical path on the activity network
Complete the table showing all the information regarding each activity that has been acquired
Activity # | Activity Identifier | Activity Duration | Precedence |
1 | A | 4 | None |
2 | B | 7 | None |
3 | C | 9 | B |
4 | D | 5 | C |
5 | E | 6 | A, D |
6 | F | 4 | C, D, E |
7 | G | 5 | F |
8 | H | 2 | G |
9 | I | 5 | G, H |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started