Questions 1 The reason that the critical path is critical is that every single activity on the path must finish on time in order for
Questions 1
The reason that the critical path is critical is that every single activity on the path must finish on time in order for the project to come in on time. A delay in any one of the critical path activities will . . .
always increase the cost of the project. | |
likely create a backlog in project work. | |
cause the entire project to be delayed. | |
always create additional risks to the project. |
Question 2
Projects with high degrees of uncertainty or those where the scope is not yet fully defined may not benefit from detailed cost calculations due to frequent changes. Instead, lightweight estimation methods can be used to generate a fast, high-level forecast of project labor costs, which can then be easily adjusted as changes arise. Detailed estimates are reserved for short-term planning horizons in a just-in-time fashion. These considerations are for projects in a __________________ environment.
deliberative | |
adaptive | |
deterministic | |
predictive |
Question 3
____________ estimating uses values, or attributes, of a previous project that are similar to the current project. Values and attributes of the projects may include but are not limited to: scope, cost, budget, duration, and measures of scale (e.g., size, weight). Comparison of these project values, or attributes, becomes the basis for estimating the same parameter or measurement for the current project.
Question 3 options:
Parametric cost | |
Bottom-up cost | |
Three-point cost | |
Analogous cost |
Question 4
Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
True | |
False |
Question 5
Match each estimating technique with the correct description.
|
|
Question 6
The resource breakdown structure is a hierarchical representation of resources by category and type, but should not be used to acquire and monitor resources.
True | |
False |
Question 7
The project budget should include management reserve funds to allow for uncertainty. Contingency reserves are set aside to manage unplanned work.
True | |
False |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started