Question
Questions 7 and 8 are about the same contract. Lou Malnati's Pizza contracts with Chi-Town Construction to build a new restaurant. It will take Chi-Town
Questions 7 and 8 are about the same contract.
Lou Malnati's Pizza contracts with Chi-Town Construction to build a new restaurant. It will take Chi-Town two years to build the restaurant. The contract price is $1.8 million. Chi-Town started construction on 1/1/2021.
The table below shows information for the two years under the contract.
Fiscal year | Construction costs incurred | Amounts billed to Lou Malnati's |
12/31/2021 | $700,000 | $1 million |
12/31/2022 | $650,000 | $800,000 |
Chi-Town management estimates the total cost of the contract to be $1.4 million as of 12/31/2021.
Assume for question 7 that the contract consists of a single performance obligation for delivery at the end of the contract.
Show what Chi-Town will report on its balance sheet and income statement accounts related to the contract for fiscal year 2021. Show your work.
Question 8
Use the facts from question 7, except assume that the contract qualifies for delivery over time treatment.
Show what Chi-Town would report on its income statement and balance sheet accounts related to the contract for fiscal year 2021.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started