Question 1: EVM Cost and Schedule Variances and Performance Indices
Suppose Jon has a project consisting of three activities. Midway through the project, he collects the following information:
Activity | PV | EV | AC |
1 | 30 | 40 | 35 |
2 | 20 | 15 | 15 |
3 | 10 | 10 | 15 |
- What are the project-level Schedule Variance (SV) and Cost Variance (CV)?
- What are the project-level Schedule Performance Index (SPI) and Cost Performance Index (CPI)?
- Under what conditions would a positive variance and a performance index less than 1.0 co-occur?
Question 2: Corrective Action
Describe any performance "thresholds" an organization uses to signal when corrective action is required to get a project back on track.