Answered step by step
Verified Expert Solution
Question
1 Approved Answer
QUESTIONS The refurbishment plan of a flat requires the painting of walls and after this, the replacement of the old floor tiles with new ones.
QUESTIONS The refurbishment plan of a flat requires the painting of walls and after this, the replacement of the old floor tiles with new ones. The original budget and planning assumptions are as follows: Wall painting Total wall area to be painted: 100 m2 Estimated Budget: 1170 Estimated duration: 5 days Planned start date: Monday Nov 18th Tile replacement Total floor area to be covered: 45 m2 Estimated Budget: 1730 Estimated duration: 4 days Planned start date: Tuesday Nov 26th At the end of Monday Nov 18th, 15m2 of the wall area had been completed and the flat owner asked for the works to be accelerated as much as possible. The crew promised to finish by the end of Thursday. At the end of Wednesday Nov 20th, 55% of the total wall area had been completed. Pick all the correct options: a. The SPI is greater than one at the end of Monday b. The crew improved their pace of work after the client asked for acceleration c. Latest data show that the crew's promise to finish on Thursday will come true d. The CPI is positive at the end of Monday e. The AC at the end of Wednesday is less than the EV for the same day Of. The SV is negative at the end of Wednesday Og. The TCPI for wall painting is greater than 1 Oh. The tile replacement will take longer than planned (4 days) Oi. The tile replacement will start as planned Oj. The refurbishment will be completed as per the times of the plan Ok. The total cost of the refurbishment will exceed the budget QUESTIONS The refurbishment plan of a flat requires the painting of walls and after this, the replacement of the old floor tiles with new ones. The original budget and planning assumptions are as follows: Wall painting Total wall area to be painted: 100 m2 Estimated Budget: 1170 Estimated duration: 5 days Planned start date: Monday Nov 18th Tile replacement Total floor area to be covered: 45 m2 Estimated Budget: 1730 Estimated duration: 4 days Planned start date: Tuesday Nov 26th At the end of Monday Nov 18th, 15m2 of the wall area had been completed and the flat owner asked for the works to be accelerated as much as possible. The crew promised to finish by the end of Thursday. At the end of Wednesday Nov 20th, 55% of the total wall area had been completed. Pick all the correct options: a. The SPI is greater than one at the end of Monday b. The crew improved their pace of work after the client asked for acceleration c. Latest data show that the crew's promise to finish on Thursday will come true d. The CPI is positive at the end of Monday e. The AC at the end of Wednesday is less than the EV for the same day Of. The SV is negative at the end of Wednesday Og. The TCPI for wall painting is greater than 1 Oh. The tile replacement will take longer than planned (4 days) Oi. The tile replacement will start as planned Oj. The refurbishment will be completed as per the times of the plan Ok. The total cost of the refurbishment will exceed the budget
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started