Question
RadarsRUs manufactures radar systems. It has just completed the manufacture of its first newly designed system, RS-32. Manufacturing data for the RS-32 follow: Direct material
RadarsRUs manufactures radar systems. It has just completed the manufacture of its first newly designed system, RS-32. Manufacturing data for the RS-32 follow:
Direct material cost | $80,000 | per unit of RS-32 |
---|---|---|
Direct manufacturing labor time for first unit | 3,100 | direct manufacturing labor-hours |
Learning curve for manufacturing labor time per radar system | 85% | cumulative average time |
Direct manufacturing labor cost | $27 | per direct manufacturing labor-hour |
Variable manufacturing overhead cost | $17 | per direct manufacturing labor-hour |
aUsing the formula for an 85% learning curve, b =
Requirement:
Calculate the total variable costs of producing 2, 4, and 8 units.
Begin by calculating the total cumulative time in labor-hours. (Round the cumulative average time per unit to the nearest whole number.)
Number of | Cumulative average time | Cumulative total time: | ||||
units | per unit: Labor-hours | Labor-hours | ||||
2 |
|
|
| |||
4 |
|
| ||||
8 |
|
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started