RadarsRUs manufactures radar systems. It has just completed the manufacture of its first newly designed system, RS-32. Manufacturing data for the RS-32 follow: Requirement Calculate
RadarsRUs manufactures radar systems. It has just completed the manufacture of its first newly designed system, RS-32. Manufacturing data for the RS-32 follow:
Requirement
Calculate the total variable costs of producing 2, 4, and 8 units.
Begin by calculating the total cumulative time in labor hours.
# of Units | Cumulative average time per unit: Labor Hrs. | Cumulative total time: Labor Hrs. |
2 | ||
4 | ||
8 |
Now, calculate the total variable costs of producing 2 units, then calculate the total variable costs for 4 and 8 units.
Variable cost of producing: | 2 units | 4 units | 8 units |
Direct Materials | |||
Direct Manufacturing labor | |||
Variable manufacturing overhead | |||
Total variable costs |
Direct material cost Direct manufacturing labor time for first unit Learning curve for manufacturing labor time per radar system Direct manufacturing labor cost Variable manufacturing overhead cost $81,000 per unit of RS-32 3,200 direct manufacturing labor-hours 85% cumulative average timea $25 per direct manufacturing labor-hour $19 per direct manufacturing labor-hour In 0.85 -0.162519 Using the formula for an 85% learning curve, b.h2. In 2 0693147
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started