rage 528 3. The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks) for
rage 528 3. The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks) for typical lot sizes, amount on hand, and the direct components of each item and, in brackets, the number of each component for each parent. LO2 & LO3 Amount on Direct Item Lead Time Hand Components End item 1 L(2). C(1), K(3) L 2 10 B(2). J(3) C 3 15 G(2), B(2) K 3 20 H(4). B(2) B 2 30 J 3 30 G 3 AA A 527 776