Question
Randolph Inc. has developed value-added standards for four activities: purchasing parts, receiving parts, moving parts, and setting up equipment. The activities, the activity drivers, the
Randolph Inc. has developed value-added standards for four activities: purchasing parts, receiving parts, moving parts, and setting up equipment. The activities, the activity drivers, the standard and actual quantities, and the price standards for 2017 are as follows:
Activities Activity Driver SQ AQ SP
Purchasing Parts Purchase Orders 3,400 3,500 $420
Receiving Parts Receiving Orders 6,700 6,860 210
Moving Parts Number of Moves 0 3,120 625
Setting up Equipment Setup Hours 0 12,380 145
Note: The actual prices paid per unit of each activity driver were equal to the standard prices.
Part A Prepare a cost report that lists the value-added, non-value-added, and actual costs for each activity.
Part B Identify which activities are non-value added and explain why. Why do value-added activities have a component of non-value-added costs?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started