Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Recently, Phil Harris, the production control manager at Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed Recently, Phil Harris, the production control manager at Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning, Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown on the next page. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram shown below. Phil noted that the gear box is assembled by the Subassembly Department and subsequently is sent to the main engine assembly line. The input shaft is one of several component parts manufactured by Brunswick that are needed to produce a gear box subassembly. Thus, levels 0, 1, and 2 are included in the product structure diagram to indicate the three manufacturing stages that are involved in producing an engine: the Engine Assembly Department, the Subassembly Department, and the Machine Shop. The manufacturing lead times required to produce the gear box and input shaft components are also indicated in the bill-of-materials diagram. Note that two weeks are required to produce a batch of gear boxes and that all the gear boxes must be delivered to the assembly-line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of input shafts, and all the shafts needed for the production of gear boxes in a given week must be delivered to the Subassembly Department stockroom before Monday morning of that week. In preparing the MRP example. Phil planned to use the worksheets shown the below and to make the following assumptions: 1. Fifteen gear boxes are on hand at the beginning of Week 1, and five gear boxes are currently on order to be delivered at the start of Week 2 2. Forty Input shafts are on hand at the start of Week 1, and 22 are scheduled for delivery at the beginning of Week 2 2. Forty input shafts are on hand at the start of Week 1, and 22 are scheduled for delivery at the beginning of Week 2. Model 1000 master schedule 4 5 6 7 8 9 10 11 12 Week T 2 3 Demand 12 5 7 10 15 23 10 12 10 Crankcase Model 1000 bill-of-material Engine assembly Gear box Lead time2 weeks Used: 1 per engine Input shaft Lead time-3 weeks Used 2 per gear box a. Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. Gear Box Requirements Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a ingle period. Calculate the net requirements and planned order releases for the gear boxes and Input shafts. Assume that lot sizing is lone using lot-for-lot Gear Box Requirements Week: Gross Requirements Scheduled Receipts Projected Available Balance Net Requirements Planned Order Receipt Planned Order Release 12 2 5 3 5 6 7 B 10 11 12 7 10 15 23 10 12 8 18 Input Shaft Requirements Week: Gross Requirements Scheduled Receipts Projected Available Balance Net Requirements Planned Order Receipt Planned Order Release 2 6. 10 11 12 Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and Input shafts. These costs are as follows: PART Gear Box COST Setup $75/order Inventory carrying cost $1/unit/week Input Shaft Setup $35/order Inventory carrying cost $2/unit/week b. Given the cost structure, evaluate the cost of the schedule from (a). Assume inventory is valued at the end of each week. Setup Inventory Total Gear Box Input Shaft Total Cost

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Principles Part 1

Authors: Jerry J. Weygandt, Donald E. Kieso, Paul D. Kimmel, Barbara Trenholm, Valerie Kinnear, Joan E. Barlow

6th Canadian edition

1118306783, 978-1118728918, 1118728912, 978-1118306789

More Books

Students also viewed these Accounting questions

Question

What is embedded SQL, and how is it used?

Answered: 1 week ago

Question

How did the states respond to the terrorist threat?

Answered: 1 week ago