Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown

Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table:

Time Estimates (days)

Activity

Optimistic

Most Likely

Pessimistic

A

6

7

10

B

4

9

10

C

4

7

8

D

1

4

5

E

5

7

a. What is the expected completion time of the project?

The expected completion time is 18 days. (Enter your response as an integer.)

b. What is the probability of completing the project in 20 days? Refer to the standard normal table.

The probability of completing the project in 20 days is __ enter your response here. (Enter your response rounded to four decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Modern Management Concepts And Skills

Authors: Samuel Certo, S Certo, S. Certo

15th Edition

0134729137, 9780134729138

More Books

Students also viewed these General Management questions