Question

1 Approved Answer

Red Company had bid on a contract to build a prototype personal computer for Black Company. Parts for this prototype will be obtained from

Red Company had bid on a contract to build a prototype personal computer for Black Company. Parts for this prototype will be obtained from outside vendors. The table below present the activities involved in this project and the various number of days involved in each event. Optimistic Time Most Likely Time Event. Time 1. Bill Awarded 2. Order parts 3. Prepare space production 4. Receive and inspect parts 5. Assemble prototype 6. Quality Assurance Testing 4 3 10 7 3 7. Ship to customer How much time (in days) is the total project expected to take? 5 8 14 10 5 Pessimistic 23497. 12 13 19

Step by Step Solution

3.41 Rating (151 Votes )

There are 3 Steps involved in it

Step: 1

Expected Duration Optimistic Time 4 Most Likely Time ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting and Reporting a Global Perspective

Authors: Michel Lebas, Herve Stolowy, Yuan Ding

4th edition

978-1408066621, 1408066629, 1408076861, 978-1408076866

More Books

Students also viewed these Accounting questions

Question

Copy and complete the statement. 3800 m ? km =

Answered: 1 week ago