Reed Enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that
Reed Enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that a project's expected NPV can be negative, in which case it will be rejected.(EXCEL/FORMULA) r: 12.00%
Year: 0 1 2 3
Cash flows: $1,000 $450 $465 $470
a. $100.01
b. $102.83
c. $107.02
d. $115.85
e. $123.03