Refer to the following table for project information: Project XYZ Task Duration (Days) Predecessors Resource (RS) A 6 1 B 4 2 C 2.5 A,

Refer to the following table for project information:

Project XYZ

Task Duration (Days) Predecessors Resource (RS)
A 6 1
B 4 2
C 2.5 A, B 1
D 8 B 2
E 5 C 2
F 2 D, E 1
G 3 F 2

Assignment requirement: To level (manually doing in the excel as examples in slidesandusing the software to check your work) the Garden project given 3 BH and 2 BH respectively.

The task names, duration, precedence relationship and resource requirement are given in that project. I set up a daily resource max units to be 4 (400%).Your assignment is to level the project if the max units is reduced to 3 (300%) and 2 (200%).

You are also required to manually level the projectgiven 300% and 200%. Students may have different leveling solutions.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel,

7th Edition

ISBN: 470226218, 978-0470226216

More Books

Students also viewed these General Management questions