Refer to the Suburban homes construction project charter from chapter 3 , WBS in chapter 7 , and project schedule in chapter 8 . The
Refer to the Suburban homes construction project charter from chapter WBS in chapter and project schedule in chapter The initial scope as identified in the project charter as mentioned below. After developing the WBS and the project schedule using the CPM method, you were asked to identify resources for all the activities identified in the schedule Develop a resource breakdown structure RBS
a Identify resources people materials, equipment, etc. required for each element
in the schedule.
Analyze resource constraints the same resource may be required for two or more activities
at the same time based on resource availability.
Develop a responsibility assignment matrix RAM and RACI table. Develop a resource
histogram for the entire project. NOTE: Choose one of the three tools to complete, not all
three.
Identify resource overloads and propose resolutions to address them by resource leveling.
Estimate time required to complete each work element by considering resource constraints.
If required, calculate the project schedule again. Compute forward pass and backward pass
to determine project duration. Determine the critical path for the project.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started