Question

1 Approved Answer

Referring to the resource load chart, assume these have six programmers rather than five. Which activit(ies) should be committed to the schedule that day? options:

Referring to the resource load chart, assume these have six programmers rather than five. Which activit(ies) should be committed to the schedule that day?

options: Activities #4 (compatibility testing), #5 (load testing), and #6 (use case testing)

Activity #5 (load testing) only

Activities #5 (load testing) and #6 (use case testing)

Activities #5 (load testing) and #4 (compatibility testing)

image text in transcribed
Initial Resource Load Chart for Software Installation Project Days Predecessor Duration ID Activity Description Activit(ies) (Days) Resources Slack 0 1 2 3 4 5 6 7 8 9 10 11 12 13 1 installation of software None 2 1 Programmer 0 1P 1P 2 configuration of settings 1 1 Programmer 0 1P 3 configuration testing 2 4 1 SW testers 0 1 SW 1 SW 4 compatibility testing 3 3 2 SW testers 2 2 SW 2 SW 2 SW SL SL 5 load testing 3 5 4 SW testers 0 4 SW 4 SW 4 SW 4 SW 4 SW 6 use case testing 3 IN 2 SW testers 3 2 SW 2 SW SL SL SL 7 employee training 4,5,6 3 Trainers O 3T 3T 3T Total Resources Required -> 1P 1P 1P 1 SW 1 SW 8 SW 8 SW 6 SW 4 SW 4SW 3T 3T 3T Total Programmers (P) 1P 1P 1P Resources Software testers (SW) 5 SW 5 SW 5 SW 5 SW 5 SW|5 SW 5 SW Available: Trainers (T) 3T 3T 3TInitial Resource Load Chart for Software Installation Project Days Predecessor Duration ID Activity Description Activit(ies) (Days) Resources Slack 0 1 2 3 4 5 6 7 8 9 10 11 12 13 1 installation of software None 2 1 Programmer 0 1P 1P 2 configuration of settings 1 1 Programmer 0 1P 3 configuration testing 2 4 1 SW testers 0 1 SW 1 SW 4 compatibility testing 3 3 2 SW testers 2 2 SW 2 SW 2 SW SL SL 5 load testing 3 5 4 SW testers 0 4 SW 4 SW 4 SW 4 SW 4 SW 6 use case testing 3 IN 2 SW testers 3 2 SW 2 SW SL SL SL 7 employee training 4,5,6 3 Trainers O 3T 3T 3T Total Resources Required -> 1P 1P 1P 1 SW 1 SW 8 SW 8 SW 6 SW 4 SW 4SW 3T 3T 3T Total Programmers (P) 1P 1P 1P Resources Software testers (SW) 5 SW 5 SW 5 SW 5 SW 5 SW|5 SW 5 SW Available: Trainers (T) 3T 3T 3T

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Planning And Control Techniques

Authors: Rory Burke

3rd Edition

047198762X, 9780471987628

More Books

Students also viewed these General Management questions

Question

Graph the given inequality. 1. y 2x + 1 2. y - 3x + 6 3. x 2 4. x 0

Answered: 1 week ago

Question

5. Talk at the right times with the right tone of voice and volume.

Answered: 1 week ago