Relevant information for a project consisting of activities A, B, , I is provided in the table below and the project network is provided. Activity
Relevant information for a project consisting of activities A, B, , I is provided in the table below and the project network is provided.
Activity | Time (in Weeks) | Cost | Immediate Predessors | ||
---|---|---|---|---|---|
Normal | Crash | Normal | Crash | ||
A | 7 | 7 | $1350 | $1350 | NA |
B | 4 | 3 | $1150 | $1360 | A |
C | 5 | 3 | $800 | $1100 | A |
D | 3 | 2 | $1800 | $1840 | B |
E | 4 | 3 | $1200 | $1210 | B |
F | 1 | 0 | $650 | $680 | C |
G | 4 | 2 | $1500 | $1580 | E, F |
H | 4 | 2 | $1650 | $1680 | D |
I | 3 | 1 | $1300 | $1680 | G, H |
The project network is: When all activities are completed in normal time, what is the critical path? Enter the letters of the activities on the path in capitals (e.g. ABCDEFG). When all activities are completed in normal time, what is the project completion time? To reduce project completion time by 1 week at minimum cost, which activity should be crashed? Enter the letter for the activity. What is the incremental cost to reduce project completion time by 1 week at minimum cost?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started