Remember Joan? The owner representative for the Library project. The project has moved through design, the contract type selected, and the project was put out
Remember Joan? The owner representative for the Library project. The project has moved
through design, the contract type selected, and the project was put out to bid. A variety of
subcontracts were developed by the General Contractor for the project. One was for site work.
One particular work package in the site work subcontract involved foundation excavation and
piping installation. This work package integrated with the foundation work package footings
are part of the concrete subcontract
Joan was really getting into the construction activities associated with the project. As such, she
wanted to verify some of the subcontract estimates. Sbe chose the foundation excavation work
package.
Joan called Chuck with several questions to get her started on estimating the cost of the trenching
work package. Later that day, Chock dropped off several tables with the rest of the information
required to complete the bid estimate, along with a short note:
We decided to wse a trwck with a trailer for hamling earth. Inctude this in the overhead"
cost and don't warny about balancing it with the loader. Include the truck and trailer
costs for all the hours warked by the foreman because they also thiclude the cost for the
thwe not used. The foreman should be on the job for about hows. Also, the concrete
footing, floor slab, and the inswlation will be done by other contractors, so don't worry
abowt them. Eyjoy:"
Table Expected prodnctivity and equipment cost
"Note: Job Efficiency Factor is already included in these productivities
Material Properties
Excavation: Swell Factor when excavated, the soil expands by into Loose Cubic
Yards
Compaction: Bedding Material Shrinkage utien compacted, bedAing shrinks
Backfill Shrinkage when compacting backfill, it shrinks
Table Required Labor
Table Cost Summary
Estimating Assignment
You are Joun, so: prepare a memo to Chock for the foundation excavation work package estimate
setting out your calculations, results, and suggestions for the estimate of the excavation. Your
solution should include the following information:
The total quantities of excavated material, beding material, and backfill measured in LCY
LCY loose cubic yards. The volume of material 'after' excavation.
The unit price SLCY and total price of each item.
The total price of the excaration. Don't forget to add profit to your estimate.
Go to the OSHA web site and find safety recommendations for trench excavation. As you
finshed the estimate, you checked the OSHA regulations for trenching and you found some
very important information that you want to share.
Atrach all of your calculations as a supplement to the memo.
Feundation Excavabion Work Items to be priced
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started