Remember Joan? The owner representative for the Library project. The project has moved through design, the contract type selected, and the project was put out

Remember Joan? The owner representative for the Library project. The project has moved
through design, the contract type selected, and the project was put out to bid. A variety of
subcontracts were developed by the General Contractor for the project. One was for site work.
One particular work package in the site work subcontract involved foundation excavation and
piping installation. This work package integrated with the foundation work package (footings
are part of the concrete subcontract)
Joan was really getting into the construction activities associated with the project. As such, she
wanted to verify some of the subcontract estimates. Sbe chose the foundation excavation work
package.
Joan called Chuck with several questions to get her started on estimating the cost of the trenching
work package. Later that day, Chock dropped off several tables with the rest of the information
required to complete the bid estimate, along with a short note:
"We decided to wse a trwck with a trailer for hamling earth. Inctude this in the overhead"
cost and don't warny about balancing it with the loader. Include the truck and trailer
costs for all the hours warked by the foreman because they also thiclude the cost for the
thwe not used. The foreman should be on the job for about 172 hows. Also, the concrete
footing, floor slab, and the inswlation will be done by other contractors, so don't worry
abowt them. Eyjoy:"
Table 1 Expected prodnctivity and equipment cost
"Note: Job Efficiency Factor is already included in these productivities
Material Properties
Excavation: Swell Factor =25%(when excavated, the soil expands by 25% into Loose Cubic
Yards)
Compaction: Bedding Material Shrinkage -6.8%(utien compacted, bedAing shrinks 6.8%)
Backfill Shrinkage =10.8%(when compacting backfill, it shrinks 10.8%)
Table 2 Required Labor
Table 3 Cost Summary
Estimating Assignment
You are Joun, so: prepare a memo to Chock for the foundation excavation work package estimate
setting out your calculations, results, and suggestions for the estimate of the excavation. Your
solution should include the following information:
The total quantities of excavated material, beding material, and backfill measured in LCY.
LCY = loose cubic yards. The volume of material 'after' excavation.
The unit price (S/LCY) and total price of each item.
The total price of the excaration. Don't forget to add profit to your estimate.
Go to the OSHA web site and find safety recommendations for trench excavation. As you
finshed the estimate, you checked the OSHA regulations for trenching and you found some
very important information that you want to share.
Atrach all of your calculations as a supplement to the memo.
Feundation Excavabion Work Items to be priced
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel,

7th Edition

470226218, 978-0470226216

More Books

Students also viewed these General Management questions