Question

1 Approved Answer

Report from Team of Tunnel Consultants: Overall, it should take three years to complete construction of the tunnel. The project would require the upfront purchase

image text in transcribed
image text in transcribed
Report from Team of Tunnel Consultants: Overall, it should take three years to complete construction of the tunnel. The project would require the upfront purchase (t=0) of a $100 million Blade Digger, a huge machine to drill the tunnel. The Blade Digger has a useful life of five years, and can be depreciated at a rate of $20M/year. Based on our analyses, we anticipate that, at any point in time, The Blade Digger can be sold at book value. We expect annual construction expenses of $50M / year for 3 years (from t=1, 2, 3) and annual maintenance expenses of $25M / year throughout the 30-year life of the tunnel, with maintenance expenses to be paid beginning at time t=4. We expect that the tunnel has no salvage value at the end of its useful life. The NWC requirement during the construction phase of this project is $15M (from t=0, 1, 2). We anticipate a $5M NWC requirement from t=3 and on. We estimate that, throughout life of tunnel, about 3.5 million vehicles will use the tunnel per yean Your relevant marginal tax rate is 35%, and based on the risks involved, the opportunity cost of capital is assessed to be 15%. Be sure to include all of your names on the first page of your homework submission. Please make sure that the final work-product is in a printable format

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Forecasting Methods And Applications

Authors: Spyros G. Makridakis, Steven C. Wheelwright, Rob J Hyndman

3rd Edition

0471532339, 9780471532330

More Books

Students also viewed these Finance questions

Question

What is meant by planning or define planning?

Answered: 1 week ago

Question

Define span of management or define span of control ?

Answered: 1 week ago

Question

What is meant by formal organisation ?

Answered: 1 week ago

Question

What is meant by staff authority ?

Answered: 1 week ago