REQUEST FOR SYSTEM SERVICES Date: August 13, 2023 Submitted by : Gerald Bandow Department or Office Information Technology Company Name: Central City Library Stakeholders :
REQUEST FOR SYSTEM SERVICES
Date: August 13, 2023
Submitted by: Gerald Bandow
Department or Office Information Technology
Company Name: Central City Library
Stakeholders: Library management, staff, patrons, and suppliers
Business Product/Service: Library services, including book lending, cataloging, digital media access, etc.
Functional System Name: Library Management System (LMS)
Type of Request: ___ New System - no current computer support
__x_ Redesign current computer-based system
Problem Statement or Request Description:
The existing Library Management System (LMS) lacks efficiency in managing inventory, user registrations, digital media access, and reporting functionalities. Specific issues include:
What is or is not happening? Delays in updating inventory, difficulties in tracking overdue books, inefficient user registration process.
When and how often does this happen? Daily, impacting staff workflow and patron satisfaction.
Who or what departments are affected? Library staff, management, patrons, and suppliers.
When this situation occurs what is the result? Late reports, unhappy patrons, increased labor time, potential loss of revenue.
The System Development Life Cycle I will use the Agile model for this project because of its flexibility, adaptability, and emphasis on customer collaboration. This approach will allow for ongoing feedback and iterative development, ensuring that the new system aligns with the library's evolving needs.
The above is what I did in week one that I somehow need to go off of for Week Three. below here I need to use the information from above to set up a plan.
Central City Library
Office information Technology
Project Plan
Version: 1.0
Prepared by:
Gerald Bandow
August 27, 2023
Table of Contents
Table of Contents................................................................................................................................................................................2
Executive Summary.............................................................................................................................................................................3
Introduction............................................................................................................................................................................................4
Purpose of this document........................................................................................................................................................................4
Background..................................................................................................................................................................................................4
Project Purpose...........................................................................................................................................................................................4
Project Assumptions and Constraints...............................................................................................................................................4
Assumptions:...............................................................................................................................................................................................4
Constraints:................................................................................................................................................................................................4
Scope Management..............................................................................................................................................................................4
Project Scope Statement.........................................................................................................................................................................4
Hardware/software requirments........................................................................................................................................5
Interface Considerations............................................................................................................................................................5
Network Diagram.................................................................................................................................................................................6
Team Management................................................................................................................................................................................6
Team Directory...........................................................................................................................................................................................6
Executive Summary
Introduction
Purpose of this document
The purpose of the Project Plan is to define the hardware and software requirements. In addition, it will include interface considerations, a network diagram and the scope of the project.
Background
Project Purpose
.
Project Assumptions and Constraints
Assumptions:
Constraints:
Scope Management
Scope Management involves the identification of all the work required, and only the work required, to complete the project successfully.
Project Scope Statement
.
Hardware/software requirEments
- Symantec Antivirus
Interface Considerations
Network Diagram
Team Management
.
Issues
Teamwork
The project team is only as strong as the weakest link. Creating a chained approach to solving issues will help build communications to the stakeholders. Ultimately, communication will help the project succeed or lack of communication will end up making the project struggle.
Relationships among projectteammembers are critical to project success. You don't have to be friends, but you do have to be coworkers andteamplayers. If sound working relationships are not present among the projectteamor stakeholders, there will be problems.
- The project manager can schedule team building activities outside of the office like going to a sports event, attending a comedian show, or a viewing of an art gallery. These outside events can build relationships and help members relate to each other. It will also build the communication especially with a team that may not be as familiar with each other.
Team Directory
The following is a list of all team members on the project.
Role | Name | Department | Phone Number | Email Address |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started