require CPM Chart for the below activity and identify the critical path Activity Activity Annotation Activity Duration Preceding Activities A Team Formation 3(1st - 3

image text in transcribed

require CPM Chart for the below activity and identify the critical path

image text in transcribed
Activity Activity Annotation Activity Duration Preceding Activities A Team Formation 3(1st - 3 d November 2021) B Graphic Designing 6 (4th -10th November 2021) A C Printing 2 (10th -12th November 2021) B D Awareness Program 15 (13th - 28th November 2021) C and rallies E Promotions And 46 (15th Nov- 31th Dec 2021) D Marketing Collecting 39 (16th Nov- 25th Dec 2021) E Recyclable goods G Selling Coupons 48 (17th Nov 2021 - 1st Jan 2022) F H Invitations To 1 (20th Nov - 21st Nov 2021) G venders Venue Selection and 5 (10th Dec-15th Dec 2021) H Booking J Booths Decorations 1 (31 Dec 2021) I and setting K Selling Goods 1 (1 =t Jan 2022) J L Collecting profits 1 (2nd Jan -3"d Jan 2022) K and Handing it to Student funds

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Marketing And Export Management

Authors: Gerald Albaum , Alexander Josiassen , Edwin Duerr

8th Edition

1292016922, 978-1292016924

Students also viewed these Economics questions

Question

=+a) Whether to invest in solar energy companies.

Answered: 1 week ago