Required information Exercise 2-15 (Algo) Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.] Delph Company uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company estimated that 51,000 machine-hours would be required for the period's estimated level of production. It also estimated $1,020,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $5.00 per machine-hour. Because Delph has two manufacturing departments-Molding and Fabrication-it is considering replacing its plantwide overhead rate with departmental rates that would also be based on machine-hours. The company gathered the following information to enable calculating departmental overhead rates: During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs-Job D-70 and Job C-200. It provided the following information related to those two jobs: During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobs-Job D-70 and Job C-200. It provided the following information related to those two jobs: Delph had no underapplied or overapplied manufacturing overhead during the year. Exercise 2-15 (Algo) Part 2 Required: 2. Assume Delph uses departmental predetermined overhead rates based on machine-hours.. a. Compute the departmental predetermined overhead rates. b. Compute the total manufacturing cost assigned to Job D-70 atid Job C-200. c. If Delph establishes bid prices that are 150% of total manufacturing cost, what bid prices would it have established for Job D-70 and Job C-200? d. What is Delph's cost of goods sold for the year