Question
Required information Skip to question [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to
Required information
Skip to question
[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:
2021 | 2022 | 2023 | |||||||
Cost incurred during the year | $ | 2,581,000 | $ | 2,347,000 | $ | 3,049,200 | |||
Estimated costs to complete as of year-end | 6,319,000 | 2,772,000 | 0 | ||||||
Billings during the year | 2,090,000 | 2,838,000 | 5,072,000 | ||||||
Cash collections during the year | 1,845,000 | 2,900,000 | 5,255,000 | ||||||
Westgate recognizes revenue over time according to percentage of completion.
2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred). 2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).
REQUIRED 2A
Record construction costs.
Record progress billings.
Record cash collections.
Record gross profit (loss).
REQUIRED 2B
Record construction costs.
Record progress billings. Record cash collections.
Record gross profit (loss).
REQUIRED 2C
Record construction costs.
Record progress billings.
Record cash collections.
Record gross profit (loss).
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started